Schedule Performance Report
  • 04 Mar 2024
  • 1 Minute to read
  • Contributors
  • Dark
    Light
  • PDF

Schedule Performance Report

  • Dark
    Light
  • PDF

Article summary

The Schedule Performance Report

The Schedule Performance Report supplements the Progress Summary and Six Period reports. The report has a fixed format, meaning that it contains a set of fixed columns. However, some configuration options remain, like grouping, selecting cut-off and period start dates, adding background colors, and defining and applying Safran filters.

SP Schedule Performance Properties

The report columns are:

ColumnDescription
ID/CodeShows Activity ID or Group Code.
DescriptionShows activity description or group code description.
Original ContractDivided in two columns, periodic planned and cumulative to date. The Original Contract is the value from the first baseline.
Current BaselineThis is divided into two columns. The Current baseline is the value from the last baseline.
ForecastDivided into two columns. The forecast is the value from the current scope and current plan.
ActualThe actual column shows periodic and cumulative, % complete weighted against the Baseline scope.

SP Schedule Performance Report