Documentation Index

Fetch the complete documentation index at: https://docs.safran.com/llms.txt

Use this file to discover all available pages before exploring further.

Timenow

Prev Next

Timenow

Timenow is a critical element of a Safran Planner plan. Timenow is a defined point in time from where you see your activities. Timenow will usually be different from today's date. Timenow is the earliest possible time to plan your activities or schedule unfinished work. You will see that the Early Start date cannot be earlier than Timenow.

When activities are added to the plan using no time constraints or logic, they will, by default, get an Early Start date = Timenow. By adding logic, calendars, time constraints, etc., the network analysis will update the Early Start point of the activity.

Planners often have different ways of working with Timenow. Some like to keep Timenow stable and not touch it/move it in between baselines, while others want to move Timenow regularly. By moving Timenow, unfinished activities will be moved accordingly. If you are behind, the remaining work of your plan will be pushed out in time according to the new Timenow and the logic used between the activities.

You set the initial Timenow when you create a new Project.

Set and adjust timenow

Moving Timenow

Moving Timenow is possible. To update Timenow, you need to use the Reschedule function of the Project tab. In the Reschedule window, enter the new Timenow and click OK to update. You can move Timenow not only to a later date but also to an earlier date if needed.

Set and adjust timenow