Schedule Performance Report

The Schedule Performance Report

The Schedule Performance Report supplements the Progress Summary and Six Period reports. The report has a fixed format, meaning that it contains a set of fixed columns. However, some configuration options remain, like grouping, selecting cut-off and period start dates, adding background colors, and defining and applying Safran filters.

SP Schedule Performance Properties

The report columns are:

Column Description
ID/Code Shows Activity ID or Group Code.
Description Shows activity description or group code description.
Original Contract Divided in two columns, periodic planned and cumulative to date. The Original Contract is the value from the first baseline.
Current Baseline This is divided into two columns. The Current baseline is the value from the last baseline.
Forecast Divided into two columns. The forecast is the value from the current scope and current plan.
Actual The actual column shows periodic and cumulative, % complete weighted against the Baseline scope.

SP Schedule Performance Report