The Schedule Performance Report
The Schedule Performance Report supplements the Progress Summary and Six Period reports. The report has a fixed format, meaning that it contains a set of fixed columns. However, some configuration options remain, like grouping, selecting cut-off and period start dates, adding background colors, and defining and applying Safran filters.

The report columns are:
| Column | Description |
|---|---|
| ID/Code | Shows Activity ID or Group Code. |
| Description | Shows activity description or group code description. |
| Original Contract | Divided in two columns, periodic planned and cumulative to date. The Original Contract is the value from the first baseline. |
| Current Baseline | This is divided into two columns. The Current baseline is the value from the last baseline. |
| Forecast | Divided into two columns. The forecast is the value from the current scope and current plan. |
| Actual | The actual column shows periodic and cumulative, % complete weighted against the Baseline scope. |